Crew Hours Calculator

Labor hours and cost from start and finish times. US units, change any unit beside its field.

Measurements

$

About this calculator

Turn start and finish times into total crew hours and labor cost, ready to drop into a job.

How it’s calculated

Hours per day = finish − start − break. Total = hours × crew × days.

Worked example

With these inputs:

Start time (24h)
07:30
Finish time (24h)
16:00
Unpaid break (minutes)
30
Crew size
3
Days
5
Cost per labor hour
$40

the result is:

Total labor hours
120 h
Labor cost
$4,800.00
Crew-days
15

Tips from the trade

  • Track actual hours against quoted hours on every job. It is the fastest way to sharpen your pricing.

Results are estimates for planning and pricing. Check quantities against your drawings, the manufacturer’s data and local building codes before ordering.