Masonry is estimated by wall area. Each brick or block, together with its share of the mortar joint, covers a fixed patch of wall face. Count the area, multiply by the units per area, add waste, and you have the core of the estimate. The rest of the job is everything that turns a pile of bricks into a finished wall: mortar, ties, lintels, damp protection, footings and access.
Measure the wall
Measure each wall's length and height and multiply. Measure the length along the centre of the wall for thick walls, so corners aren't counted twice. Subtract windows and doors larger than about 1 m²; smaller openings take nearly as many cut bricks as they save. Gable ends are triangles: ½ × width × height.
Counts per area
| Unit | Face size with joint | Per area |
|---|---|---|
| Brick 215 × 65 | 225 × 75 mm | 59.3 per m² (use 60) |
| Imperial brick 225 × 70 | 235 × 80 mm | 53.2 per m² |
| Block 440 × 215 | 450 × 225 mm | 9.88 per m² (use 10) |
A double-thickness wall doubles the brick count. A cavity wall (brick outer leaf, block inner leaf) needs 60 bricks and 10 blocks for every square metre.
Waste
Add 5% for new bricks and blocks on straightforward walls, and up to 10% for reclaimed bricks, lots of cutting, piers, arches or decorative bonds. Buy all the bricks for one job at the same time. Batches vary in colour, and a patch of slightly different bricks halfway up a wall stands out for good.
Mortar
A practical rule: for every 1,000 bricks, allow about 1 tonne of building sand and 6–8 bags of 25 kg cement at a 1:4 to 1:5 mix. For every 100 blocks (100 mm), allow roughly 0.2 tonnes of sand and 2 bags of cement. Real use is higher than geometry suggests, because of droppings, full beds and the mortar left on the board at the end of the day.
Choose the mix for the job: a stronger 1:3–1:4 mix below the damp-proof course and in exposed walls, and 1:5–1:6 with plasticiser for general walls above DPC.
Don't forget
- Wall ties for cavity walls, about 2.5 per m² at standard spacing, more at openings
- Lintels over every opening, with the right bearing at each end
- DPC, cavity trays over openings and weep vents
- Movement joints and fillers on long walls
- Insulation boards or batts for cavity walls
- Scaffolding or staging above about 1.5 m
- Footings, from the footing calculator
- Cleaning: brick cleaner and the labour to wash down
Productivity and labour
A bricklayer on plain work typically lays 300–500 bricks a day, with far fewer on facework that has detailing, piers and openings. Block goes faster per square metre, but heavy 215 mm blocks slow things down. A labourer supporting each bricklayer is normal. The best rates are your own. Track bricks laid per day on every job and use the average.
A worked example
A garden wall 8 m long and 1.2 m high in standard brick, one brick thick: 9.6 m² × 120 = 1,152 bricks, plus 5% = 1,210. Mortar: about 1.2 tonnes of building sand and 9 bags of cement. Add a footing, coping and a day of cleaning.
The brick and block calculators work out counts and mortar together, and the mortar calculator handles any number of units you already know.
Measuring from drawings
When you're pricing from plans, take wall lengths from the dimensions, not by scaling the drawing. Note the wall type for each run (single skin, cavity, block, feature brick), because each has a different count and labour rate. Work through openings systematically: list every door and window with its size, then total the deductions per wall. Use the same order every time so nothing gets skipped.
Pricing the work
Once you have quantities, a masonry price has four parts: the materials at your cost, the labour at a realistic rate per thousand bricks or per square metre, plant and access (mixer, scaffold, lifting), and the extras listed above. Keep cleaning and protection as separate lines. They're easy to forget, and clients understand them when they see them written down.
Checklist before you send the price
- Every wall measured and every opening deducted
- Waste added, and the brick type and colour confirmed with the client
- Mortar, ties, lintels and damp protection listed
- Footings priced or excluded in writing
- Scaffold, skip and clean-down included
This guide is general information for estimating. It is not engineering, legal or tax advice. Check the Building Regulations and Building Control for your project.