Roof Tile Calculator

Roof area, tiles, battens, sarking and ridge capping. Metric units, change any unit beside its field.

Measurements

%
Use 10% for gables and 15% for hips and cut-up roofs.

About this calculator

Full tiled-roof takeoff: true roof area, number of concrete or terracotta tiles, battens at the right gauge, sarking rolls, ridge and hip capping, and pointing. Works for gable, hip and mono-pitch roofs.

How it’s calculated

True roof area = plan area including overhang × pitch factor, where pitch factor = √(1 + (rise ÷ run)²). Hip roofs with the same pitch on every side have the same area as a gable over the same footprint. Only the edges differ. Hip length = (half width) × √(2 + (rise ÷ run)²).

Tiles per m² depend on the gauge (exposed length) and cover width of the product. The figures used here are typical. Your tile maker’s gauge table takes priority.

Worked example

With these inputs:

Roof shape
Gable (two slopes)
Building length (wall to wall)
10 m
Building width (wall to wall)
8 m
Overhang (eaves and verge)
450 mm
Pitch entered as
Degrees
Pitch in degrees
22.5
Roof covering
Concrete tiles
Waste allowance
10%

the result is:

Roof tiles needed
1,225 tiles
Roof surface area
105 m²
Plan area (with overhang)
97.01 m²
Pitch factor
× 1.082 (22.5°, 4.97/12)
Eaves length
21.8 lin m

Tips from the trade

  • Valleys, dormers and chimneys add waste. Go to 15–20% on cut-up roofs.
  • Tile fixing (clips, nails or screws) follows AS 2050 and your site’s wind classification. For a metal sheet roof, use the roof sheeting calculator instead.
  • Order ridge material for the hips too. It is the most commonly forgotten line.

Common questions

How many roof tiles per m²?

About 10–11 for concrete tiles and 11–13 for terracotta, depending on the profile and the batten gauge.

How much ridge capping do I need?

Measure every ridge and hip. Most capping tiles cover about 370–380 mm each once lapped, so allow about 2.7 per metre.

Results are estimates for planning and pricing. Check quantities against your drawings, the manufacturer’s data and the NCC and Australian Standards before ordering.