Concrete Pier & Pad Calculator

Round or square piers, columns and post pads. Metric units, change any unit beside its field.

Measurements

%
Extra for cuts, breakage and spillage.

About this calculator

Concrete for deck footings, pergola piers, porch columns and pad foundations. Works for round tube formers and square dug pads.

How it’s calculated

Round: π × (diameter ÷ 2)² × height. Square: side A × side B × height. Multiply by the number of piers, then add waste.

Worked example

With these inputs:

Shape
Round (tube)
Diameter
300 mm
Height / depth
900 mm
Number of piers
8
Supply as
Pre-mixed bags
Bag size
25 kg
Waste allowance
10%

the result is:

Concrete needed
0.56 m³
Per pier
0.06 m³
Ready-mix order (to 0.25 m³)
0.75 m³
25 kg bag
49 bags
20 kg bag
59 bags

Tips from the trade

  • A bell or spread footing at the base adds volume. Add it as a separate square pad calculation.
  • Dug holes are wider than the tube. If you pour straight into the ground, measure the hole, not the tube size.
  • Footings must sit on firm ground below frost depth, usually at least 450–600 mm in the UK, and deeper in clay or near trees.

Common questions

How many bags for a 300 mm pier?

A 300 mm × 900 mm round pier holds about 0.064 m³, roughly six 25 kg bags with waste.

Results are estimates for planning and pricing. Check quantities against your drawings, the manufacturer’s data and the Building Regulations before ordering.