A deck looks simple, but its material list has more lines than most small jobs. Work from the ground up, and price each layer before moving to the next, so nothing is missed.
1. Layout and design decisions
Before counting anything, settle the basics: deck size and height, whether it's attached to the house with a ledger or freestanding, joist direction and spacing, beam positions, stairs and railings. Height matters most. A deck more than about 600 mm above the ground usually needs guarding, and taller decks need bracing and bigger footings. In the UK, raised decks over 300 mm high often need planning permission, so check before you quote.
2. Footings and posts
Lay out the beam lines and post spacing first. Every post needs a footing: a concrete pad or pier on firm ground, below frost depth (typically at least 450–600 mm, deeper in clay or near trees). Count footings, work out the concrete per footing, and add post bases or anchors. The pier calculator gives the concrete for any number of footings.
3. Beams and joists
Joists = deck length ÷ joist spacing + 1. Add rim and end joists, and a ledger if the deck is attached to the house. Count hangers (two per joist at a ledger or flush beam) and ties where joists sit on beams. Beams are usually two or three plies of joist-size timber, so count those pieces too.
Joist and beam sizes and spans must come from span tables, TRADA guidance or a structural engineer, with Building Control approval where needed. A calculator can count parts, but it can't size them. Composite decking often needs closer joist spacing, especially for diagonal boards.
4. Deck boards
Work in rows, not area. Rows = (deck width + gap) ÷ (board width + gap). Then choose a board length that suits the deck: a 4.8 m deck with 4.8 m boards wastes almost nothing, while a slightly longer deck forces joins in every row. Where joins are needed, stagger them and land them over doubled joists or blocking. Picture-frame borders and breaker boards add extra boards and extra framing, so count them separately.
5. Fixings
Two screws per board at every joist. On a 4.8 × 3.6 m deck that's around 650 screws. Hidden clip systems need one clip per joist crossing. Use stainless or coated fixings rated for treated timber, and the system made for composite boards.
6. Stairs and railings
Count stringers (one every 400 mm or so), treads and risers from the stair calculator. Railing posts, top and bottom rails, and spindles spaced under the 100 mm rule are a big part of the cost on raised decks. Railing posts must be through-bolted or fixed with approved hardware to resist the guard loads. A post screwed into the rim joist alone isn't enough.
7. The small stuff that adds up
- Joist tape on top of joists and beams
- Flashing and flashing tape for the ledger, so water can't get behind it
- Structural screws or bolts for the ledger
- End-grain preserver for cut ends of treated timber
- Weed membrane and gravel under low decks
- Stain or oil for the first coat, if included
Waste
10% for boards and framing is typical. Go higher for diagonal boards, picture-frame borders, angled corners or curved edges.
A worked example
A 4.8 × 3.6 m attached deck, joists at 400 mm centres spanning 3.6 m: 13 joists plus rims, a ledger and one doubled beam on four posts. Four 300 × 900 mm pads (about 0.25 m³, roughly 25 bags of 25 kg). Boards: 25 rows of 144 mm board at 4.8 m, 28 boards with waste. Screws: about 650, or four boxes of 200.
Use the deck framing, deck board and baluster calculators, adding each to the same job, to build the whole quote in minutes.
Common questions
Composite or timber?
Composite costs more up front but needs no staining and lasts longer. Timber is cheaper and easier to work, but needs regular maintenance. Price both if the client is unsure.
How long does a deck take to build?
A simple ground-level deck of this size is often two to four days for a small crew. Raised decks with stairs and railings take longer.