The biggest error in roof estimating is using the plan area. A roof is sloped, so its true surface area is always bigger than its footprint, and the steeper the pitch, the bigger the difference. On a steep roof, pricing the footprint can leave you a third short on materials. Start with the right area and the rest of the takeoff follows.
The pitch factor
Pitch factor = √(1 + (rise ÷ run)²). Multiply the plan area, including the overhangs, by this factor to get the true roof area.
| Pitch | Degrees | Factor |
|---|---|---|
| 4/12 | 18.4° | 1.054 |
| 6/12 | 26.6° | 1.118 |
| 8/12 | 33.7° | 1.202 |
| 10/12 | 39.8° | 1.302 |
| 12/12 | 45° | 1.414 |
For a hip roof where every slope has the same pitch, the same factor applies. A hip roof over a given footprint has the same area as a gable. Only the edges differ: hips instead of verges. Roofs with different pitches on different faces need each face worked out separately.
Measuring the roof
Take the building's length and width from the wall faces, then add the overhang at the eaves and verges. On complex roofs, split the plan into rectangles, one for each roof plane or wing, and work out each one. Use the drawings where you have them, and check at least one dimension on site, especially on older houses.
Tiles, slates and gauge
Tiles per m² depend on the gauge (the exposed length of each course) and the tile's cover width. Large interlocking concrete tiles run about 10 per m², plain tiles about 60 per m², and 500 × 250 slates about 20 per m². Battens are needed at every course: batten run = roof area ÷ gauge. Check the maker's gauge table for your pitch and exposure, since steeper or more exposed roofs often need a smaller gauge and so more tiles.
The edges
Measure eaves, verges, ridge, hips and valleys separately. They drive many material lines:
- Eaves course tiles, under-cloak and verge system
- Eaves trays, fascia vents and drip
- Ridge and hip tiles, plus a dry-fix system or mortar
- Valley troughs, lead or GRP valleys
- Ventilation at eaves and ridge
- Flashings at walls, chimneys and roof windows
Hip length = (half the building width) × hip factor, where hip factor = √(2 + (rise ÷ run)²). Valleys use the same factor.
Underlayment
Breathable membrane comes in 1 m × 50 m rolls. Allow about 15% for laps. HR (high-resistance) felts need more roof ventilation than LR (low-resistance) membranes, so the underlay choice affects the ventilation line too.
Fixings and sundries
Tile clips or nails as the maker specifies for your wind zone, batten nails, and ridge and verge fixings. Coastal and exposed sites usually need every tile fixed.
Check the minimum pitch
Every tile and slate has a minimum pitch that depends on exposure zone and headlap. Plain tiles typically need 35°; some large interlocking tiles go as low as 12.5–17.5°. Below the minimum the roof will leak no matter how well it's laid.
Don't forget the rest of the job
- Tear-off and disposal of the old roof (price by m², and by layer)
- Sarking or boarding repairs, priced as an allowance
- Scaffolding or edge protection
- Gutters, if they're being replaced
- Skips
The roofing calculator works all of this out for gable, hip and mono-pitch roofs, and the roof pitch calculator converts between every pitch format.
A worked example
A 10 × 8 m house with 300 mm overhangs and a 35° pitch, in interlocking concrete tiles: plan area 10.6 × 8.6 = 91.2 m². True roof area 91.2 × 1.221 = 111.3 m². With 10% waste at about 10 tiles per m², 1,212 tiles. Battens at 345 mm gauge: about 355 m, or 74 lengths of 4.8 m. Three rolls of membrane, and ridge tiles for 10.6 m of ridge.
Pricing checklist
- Area from the plan × pitch factor, not from the footprint
- Waste set for the roof's complexity
- Every edge measured and its materials listed
- Underlay, ventilation and flashings included
- Tear-off, disposal and repairs priced or excluded in writing
- Access, edge protection and skips included
Reading the roof on site
Before you price, walk the roof or inspect it from a ladder or drone. Note anything that adds work: soft or sagging areas, which point to rotten boarding or rafters; old layers that must come off; chimneys that need new flashing or repointing; skylights and vents; and how close the roof is to power lines, trees and neighbours. Photograph everything. The photos back up your price, and they help if there's a dispute later about what was there before you started.