Mortar volume per unit uses practical rates: about 0.55 m³ per 1,000 bricks and about 0.0011 m³ per 100 mm of block thickness. The wet volume is multiplied by 1.3 for dry materials, then split by the mix ratio. The default 1:1:6 cement:lime:sand is the M3 mortar AS 3700 deems suitable for most general brickwork.
Worked example
With these inputs:
- Laying
- Bricks
- Number of units
- 1000
- Mortar mix
- 1:1:6 cement:lime:sand (M3, general)
- Waste allowance
- 10%
the result is:
- Mortar for 1,000 bricks
- 8 × 20 kg cement + 3 × 20 kg lime + 0.6 m³ brickies sand
- Mortar volume (wet)
- 0.61 m³
- Mix 1:1:6 needs
- 8 × 20 kg cement + 3 × 20 kg lime + 0.6 m³ brickies sand
Tips from the trade
- Make only as much mortar as you can use in about 2 hours.
- Plasticiser makes the mix easier to work at 1:6, but don’t overdose it.
- Below the damp-proof course and in exposed walls, use a stronger mix.
Results are estimates for planning and pricing. Check quantities against your drawings, the manufacturer’s data and the NCC and Australian Standards before ordering.